BESS Integration – EMS/SCADA Signal Mapping & SAT Closure

KSA (Eastern Province) | Energy Storage | 30–60 MW / 60–120 MWh
A BESS project faced delays due to ambiguous signal ownership, incomplete mapping between PCS/BMS/EMS/SCADA, and repetitive SAT punch items.

What we did

  • Verified I/O list and signal mapping (status/alarms/commands/measurements) end-to-end
  • Created a SAT closure matrix tied to evidence (screenshots, test logs, sign-off lines)
  • Defined alarm grouping and response actions for operations handover

Outcome

  • Reduced SAT churn and avoided re-testing loops
  • Cleaner handover pack that operations could actually use